At 1000 Main Ave., the old Olde Tymer's Cafe building is under major renovation. Owner Sean Dugan bought it in 2024 hoping to renovate it and lease it to a new tenant. Once he saw the structural problems, he decided the interior and infrastructure needed a full overhaul. In 2023 the previous owner, Mark Cavelli, told the Durango Herald that the floors were "rotting a little bit," the hood vents were too small and the swamp coolers couldn't keep up in summer. Dugan now says the work will probably be done by the end of the year and a new restaurant will move in.
That building fits a wider pattern in-town Durango this fall. The projects that changed how people get around town over the summer are mostly set to finish before the holiday events start. The project that would change how Main Avenue looks is the one with no construction date. As of early October 2026, the downtown winter will be a season of things wrapping up, plus one long-running question that stays open.
The status board, as of the first week of October
| Project | Where | Status now | What the City or CDOT says comes next |
|---|---|---|---|
| Roosa Safety and Connectivity Project | Roosa Ave., 9th St. to El Paso St. | Under construction | Completion by end of November |
| US 160 resurfacing | Durango to Elmore's Corner | Under construction | Timeline runs through November 2026 |
| Animas River Trail main corridor | East of the river, 29th St. to Demon Bridge | Set to reopen when Phase 2 began | Phase 2 underway as of early October |
| Rio Vista Circle spur | Off the Animas River Trail | Closed, detour posted | Being rebuilt in Phase 2 |
| Demon Bridge | Animas River Trail | Open | New bridge planned for next spring |
| Downtown's Next Step | Main Avenue | 100% design complete | Construction not anticipated |
| Camino Crossing underpass | Near 12th St. | In design | Needs future grant funding |
| 1000 Main Ave. | Former Olde Tymer's | Under renovation | Likely done by year-end |
Sources for the rows above: the City's October 4 construction report for Roosa and Demon Bridge, the City's Animas River Trail project page, CDOT, the City's Downtown's Next Step and Camino Crossing pages, and the Herald.
Roosa Avenue gets permanent sidewalk by Thanksgiving
The Roosa project is the closest to a finished, permanent change. It adds about 1,300 feet of sidewalk, protected bike lanes, ADA ramps, transit-stop upgrades and intersection work between 9th Street and El Paso Street. The City expects it to be done by the end of November. Until then, Avenida del Sol is closed for underground utility work, and Roosa drops to one lane each way during work hours. The Manna Soup Kitchen transit stop stays open throughout.
East of town, CDOT's US 160 resurfacing between Durango and Elmore's Corner follows a similar schedule. It includes deck repairs and resurfacing on the Durango High Bridge, plus new ADA ramps at Dominguez Drive, River Road, Three Springs Boulevard and Elmore's Corner. CDOT's timeline runs from March 2026 to November 2026. Until it wraps up, CDOT lists overnight work from Sunday night through Friday morning, lane shifts and closures around the clock, and possible daytime delays of up to 15 minutes.
If both projects meet their dates, the two biggest construction zones on in-town and eastbound routes will be gone before the Cascade Canyon Winter Train makes its first run of the season.
The river trail's last spur and bridge carry into 2027
The Animas River Trail sits between finished and waiting. Phase 1 of the Rank Park to Memorial Park segment started June 8, 2026, and closed the trail east of the river between the 29th Street parking lot and the Rio Vista spur. The City's August update said that main corridor would reopen once construction moved to Phase 2. As of the week of October 5, Phase 2 has started, and the City expects it to last two to three months.
Phase 2 is rebuilding the spur between the trail and Rio Vista Circle, with better grades, a new surface, drainage fixes and more trees. The spur stays closed while the work goes on. The soft-surface Rea Trail is still open between the south end of Riverview Drive and the access corridor connecting Rio Vista Circle and north Riverview Drive. There is also clearing on the west side of the river this fall. The City says it is required by environmental permits that protect the endangered New Mexico Meadow Jumping Mouse, and it is being done early so the mice don't build winter hibernation nests in the work area.
Demon Bridge is open now. Crews are building abutments for its replacement, and the City plans to install the new bridge next spring. The new footbridge will be wider and have smoother abutments. It is designed to meet waterway freeboard requirements without changing the grade of the existing railroad crossing. The segment plan also calls for safer turns at the Rank Park, Rec Center spur and railroad-crossing intersection. It adds a formal soft-surface shortcut with boulder steps and a continuous 2-foot soft-surface running path, built to the City's standard of concrete at least 10 feet wide with lighting along its length. The City's timeline puts project completion in 2027.
Through the fall, trail users are asked to follow the posted detour signs around the spur work. The finished version arrives with the bridge in 2027.
Main Avenue's bump-outs are designed, but no build is planned
Downtown's Next Step is the one on this list that isn't heading toward construction. The City says its engineering team, MIG, finished the 100% streetscape and utility plans and cost estimates in August 2026. Those plans go to City Council at a study session on Tuesday, October 6, 2026, at 2 p.m. at City Hall. The project page still says construction is not anticipated. That follows a September 17, 2024, council resolution that told staff to finish the design and pilot project, not to pursue construction, and to suspend spending on that phase.
The design phase cost $1,318,896. A $640,000 grant from the Colorado Department of Local Affairs covered part of it, and $678,896 came from the City's 2015 Half Cent Sales and Use Tax Fund. That figure covers design only. The Herald's August 31 story on the finished plans did not report a construction cost.
The same Herald story showed where downtown business voices differ. Property owner Jack Turner supported infrastructure repairs but opposed a full reconfiguration of the streetscape. Claire Carver of Carver Brewing supported the bump-out concept and asked for clear, phased communication if construction ever happens.
What people can see on the street is the pilot. The temporary curb extensions and pedlets went back in for summer 2026. Last year the City took them out for the winter during the first week of November, November 3 through 7. The City hasn't posted a 2026 removal date yet. If the 2025 schedule holds, Main Avenue's winter layout will look like it did before the pilot. That is a guess based on last year, not a City announcement.
The Camino Crossing underpass near 12th Street is in a similar spot. It is still in design, and the City says building it will require future grant funding. The Buckley Park Master Plan is another plan-stage project. The City presents the completed plan on October 12 from 4 to 6 p.m., and the plan is meant to guide later decisions on improvements, costs and implementation. It does not set a start date for construction.
The storefronts that change before the streetscape does
Main Avenue's layout is staying put for now, but its storefronts keep changing. The Durango Business Improvement District's September 23 newsletter listed The Pub as open at 2075 Main Ave. It also listed Sprout of Rocky Mountain Children's Company, a children's resale boutique, at 120 W. 9th St., Unit B. Earlier this year, The Wilds Tavern opened May 1 at 741 Main Ave., in the space Switchback Taco used to occupy.
At 1000 Main, Dugan isn't naming the restaurant yet. He confirmed it won't be Olde Tymer's Cafe again, despite rumors, and he'll be a part owner of the new restaurant. He told the Herald:
"I put so much heart and love into this rehab. I didn't want to just stick it with someone. We're forming a partnership, and we're going to work together on putting the restaurant in."
He also said the new place might pay homage to Olde Tymer's, but that nothing has been finalized.
The winter calendar, in order
These dates mostly fall after the Roosa and US 160 crews are scheduled to finish. The Downtown Durango event page doesn't show a publish date, so confirm details with organizers before you go.
- October 10, 5 a.m. to 2 p.m. Main Avenue closes from 9th to 13th streets for the Second Saturdays market, Apple(less) Days and Fire Prevention Day.
- October 12, 4 to 6 p.m. Buckley Park Master Plan presentation.
- November 20. The Durango & Silverton's Cascade Canyon Winter Train begins select operating dates, departing the Durango Depot at 9:15 a.m. and running through April 30.
- November 27. Singing with Santa, with a carol walk down Main Avenue to Buckley Park for the community tree lighting.
- December 4. Downtown Noel Night, with the Festival of Trees running December 4 through 6 at the Durango & Silverton Narrow Gauge Railroad Museum.
- December 11 through 13. The Nutcracker.
- Through January 2, 2027. The Polar Express season, which starts in November.
- January 22 through 31, 2027. Snowdown, including the Parade of Lights on Main Avenue.
The City's weekly Orange Cone Report lists current closures and changes from week to week, so check the latest one before planning around any of the construction dates above.
If you own near Roosa Avenue, the Rio Vista spur or the Main Avenue blocks the pilot covers, and you're wondering how these projects affect what your home is worth, Jeremy Deas at SWCO Home Sales can walk you through it. Start with a Free Home Valuation, and I'll factor in which projects are finished and which are still waiting.